Competitor Cost Benchmark
Food Ingredients
Competitive Benchmark
Techno-Economic Analysis
A food ingredients company competes with a rival technology that makes the same product. The rival's costs are not public. In four weeks, Roebling built an engineering-based model of the rival process in the U.S. Midwest and in China, with tariffs and shipping included, resulting in an independent cost basis across 80+ scenarios and a ranked view of what drives the competitor's cost.
4 weeks
from kickoff to a working cost model of the competitor's process
80+ scenarios
across locations, feedstocks, equipment options, and production scales
U.S. vs. China
compared with tariffs, shipping, and local labor productivity built in
Challenge
The company's planning and investment case depends on a number it cannot look up: what the rival technology costs to build and run at commercial scale. Public data is thin. The one existing facility's reported capital cost reflects a different time and place than a new build today.
Solution
Roebling reconstructed the rival process from first principles, from mass and energy balance through sized equipment, and costed it with budgetary raw material quotes and its own equipment cost database. Where public data stopped, Roebling's fermentation engineers made and documented the calls.
Results
The company now has an independent cost basis for its main competing technology, with every location, feedstock, and equipment case carried through to CapEx and fully loaded COGS. Tornado diagrams rank the variables that move the competitor's cost most, showing where that cost is most exposed.
Deliverables
Process & Engineering
Block Flow Diagram
The alternative process from fermentation through final product.
Mass & Energy Balance
Material and energy flows at each production scale.
Sized Equipment List
Equipment sized for the commercial facility.
Equipment Trade-Off Analysis
A key equipment choice compared on CapEx, OpEx, and utility use.
Labor Model & Staffing Plan
Staffing adjusted for local labor productivity.
Cost & Economics
Techno-Economic Model
A dynamic model with a feedstock toggle so it can run on either feedstock.
Raw Material Quotes
Budgetary quotes collected for raw materials.
CapEx Estimates
Estimated at +/-30% for the U.S. Midwest and +/-50% for China.
COGS Breakdown
Direct and fully loaded COGS, including tariff and shipping costs.
Pro Forma Financial Model
Sources and uses, with fully loaded COGS that includes the cost of capital.
Scenario Analyses & Tornado Diagrams
Stacked upside and downside cases at three scales, with tornados for direct and fully loaded COGS.
Benchmark & Reporting
Location Comparison
A U.S. Midwest facility compared against a facility in China.
Feedstock Comparison
Two feedstock strategies compared on the same basis.
Existing Facility Cost Perspective
A high-level view of an existing facility's capital cost from public sources, alongside an estimate for a similar U.S. build today.
TEA Summary Report
Findings and key cost drivers for planning and investment decisions.
The Approach
Engineering judgment where public data stops.
One model carried every location, feedstock, and equipment case through to CapEx, direct COGS, and fully loaded COGS on the same basis.
Budgetary raw material quotes and Roebling’s equipment cost database grounded the estimate.
Tariff, shipping, and local labor productivity were built into the location comparison.
Stacked upside and downside cases ran at three production scales.